Pinpoint Test I: TCM
Pinpoint Tests - OSC Equipped Vehicle
PINPOINT TEST I: TCM
NOTE: Refer to the Transmission Control Module (TCM) Connector illustration Transaxle Connector Layouts Transaxle Connector Layouts.
NOTE: Refer to the Transmission Control Module (TCM) Relay Connector illustration Transaxle Connector Layouts Transaxle Connector Layouts.
-------------------------------------------------
I1 CHECK SJB Fuse 26 (7.5A)
- Ignition OFF.
- Check fuse: Smart Junction Box (SJB) 26 (7.5A).
- Is the resistance less than 5 ohms?
Yes
GO to I2.
No
REPAIR circuit CBP18 (GY/OG) for a short to ground. TEST the system for normal operation.
-------------------------------------------------
I2 CHECK CIRCUIT CBP18 (GY/OG) FOR AN OPEN
- Disconnect: SJB Fuse 26 (7.5A).
- Disconnect: Transmission Control Module (TCM) Relay.
- Measure the resistance between the output side of SJB fuse 26 (7.5A) and TCM relay pin 86, circuit CBP18 (GY/OG).
- Is the resistance less than 5 ohms?
Yes
GO to I3.
No
REPAIR circuit CBP18 (GY/OG) for an open. TEST the system for normal operation.
-------------------------------------------------
I3 CHECK RE406 (GY/VT) FOR AN OPEN
- Measure the voltage between TCM relay pin 86, circuit CBP18 (GY/OG) and TCM relay pin 85, circuit RE406 (GY/VT).
- Is the voltage greater than 10 volts?
Yes
GO to I6.
No
GO to I4.
-------------------------------------------------
I4 CHECK THE TCM GROUND CIRCUIT
- Disconnect: TCM C2352B.
- Measure the resistance between TCM relay pin 85, circuit RE406 (GY/VT) and TCM C2353B-16, circuit RE406 (GY/VT).
- Is the resistance less than 5 ohms?
Yes
GO to I5.
No
REPAIR circuit RE406 (GY/VT) for an open. TEST the system for normal operation.
-------------------------------------------------
I5 CHECK THE TCM GROUND SUPPLY CIRCUIT FOR AN OPEN
- Disconnect: TCM C2352A.
- Measure the resistance between TCM C2352A-1, circuit GD120 (BK/GN) and ground.
- Measure the resistance between C2352A-9, circuit GD120 (BK/GN) and ground.
- Is the resistance less than 5 ohms?
Yes
INSTALL a new TCM. TEST the system for normal operation.
No
REPAIR circuit GD120 (BK/GN) for an open. TEST the system for normal operation.
-------------------------------------------------
I6 CHECK BJB 16 (15A)
- Check fuse: Battery Junction Box (BJB) 16 (15A).
- Is the resistance less than 5 ohms?
Yes
GO to I8.
No
GO to I7.
-------------------------------------------------
I7 CHECK CIRCUIT SBB16 (VT/RD) FOR A SHORT TO GROUND
- Disconnect: BJB Fuse 16 (15A).
- Measure the resistance between the output side of BJB fuse 16 (15A), circuit SBB16 (VT/RD) and ground.
- Is the resistance greater than 10,000 ohms?
Yes
GO to I9.
No
REPAIR circuit SBB16 (VT/RD) for a short to ground. TEST the system for normal operation.
-------------------------------------------------
I8 CHECK CIRCUIT SBB16 (VT/RD) FOR AN OPEN
- Measure the resistance between the output side of BJB fuse 16 (15A), and TCM relay pin 30, circuit SBB16 (VT/RD).
- Is the resistance less than 5 ohms?
Yes
GO to I10.
No
REPAIR circuit SBB16 (VT/RD) for an open. TEST the system for normal operation.
-------------------------------------------------
I9 CHECK THE TCM POWER CIRCUIT FOR A SHORT TO GROUND
- Disconnect: TCM C2352A.
- Disconnect: Intermediate Shaft Speed Sensor C1088.
- Disconnect: Output Shaft Speed (OSS) Sensor C193.
- Measure the resistance between TCM relay pin 87, circuit CE613 (VT/BK) and ground.
- Is the resistance greater than 10,000 ohms?
Yes
INSTALL a new TCM. TEST the system for normal operation.
No
REPAIR circuit CE613 (VT/BK). TEST the system for normal operation.
-------------------------------------------------
I10 CHECK THE TCM POWER SUPPLY FOR AN OPEN CIRCUIT
- Measure the resistance between TCM relay pin 87 and TCM C2352A-2, circuit CE613 (WH/VT).
- Measure the resistance between TCM relay pin 87 and C2352A-10, circuit CE613 (WH/VT).
- Is the resistance less than 5 ohms?
Yes
GO to I11.
No
REPAIR circuit CE613 (WH/VT) for an open. TEST the system for normal operation.
-------------------------------------------------
I11 CHECK FOR POWER FROM THE SJB
- Ignition ON.
- Measure the voltage between TCM C2352A-3 and ground.
- Is the voltage greater than 10 volts?
Yes
INSTALL a new TCM. TEST the system for normal operation.
No
REPAIR circuit SBP07 (WH/RD). TEST the system for normal operation.
-------------------------------------------------