FREE REPAIR MANUALS & LABOR GUIDES 1982-2013 Vehicles
Courtesy of Operation CHARM: Car repair manuals for everyone.

Shift Interlock: Testing and Inspection

ELECTRIC CONTROL COMPONENTS INSPECTION

1. Inspect Shift Lock Control Computer








Using a voltmeter, measure the voltage at each terminals.

HINT: Do not disconnect the computer connector.

2. Inspect Shaft Lock Solenoid

(a) Disconnect the solenoid connector.





(b) Using an ohmmeter, measure the resistance between terminals.

Standard resistance: 21 - 27





(c) Apply the battery voltage between terminals. Check that an operation noise can be heard from the solenoid.

3. Inspect Key Interlock Solenoid

(a) Disconnect the solenoid connector.





(b) Using an ohmmeter, measure the resistance between terminals.

Standard resistance: 12.5 - 16.5





(c) Apply the battery voltage between terminals. Check that an operation noise can be heard from the solenoid.

4. Inspect Shift Lock Control Switch








Inspect that there is continuity between each terminals.