Canister Purge Solenoid: Testing and Inspection
1. REMOVE VSV.(a) Disconnect the following connector and hoses:
(1) Connector
(2) Hose (from charcoal canister) from port E of VSV
(3) Hose (from air intake chamber) from port F of VSV
(b) Remove the bolt and VSV.
2. INSPECT VSV.
(A) Inspect VSV for open circuit.
- Using an ohmmeter, check that there is continuity between the terminals.
Resistance at 20°C (68°F): 30 - 34 Ohms
^ If resistance is not as specified, replace the VSV.
(B) Inspect VSV for ground.
- Using an ohmmeter, check that there is no continuity between each terminal and the body.
^ If there is continuity, replace the VSV.
(C) Inspect VSV operation.
(1) Check that the air does not flow from port E to port F.
(2) Apply battery voltage across the terminals.
(3) Check that the air flows from port E to port F.
^ If operation is not as specified, replace the VSV.
3. REINSTALL VSV.
(a) Install the VSV with the bolt.
(b) Connect the following connector and hoses:
(1) Connector
(2) Hose (from charcoal canister) to port E of VSV
(3) Hose (from air intake chamber) to port F of VSV