Installation
TX6A AUTOMATIC TRANSMISSION / TRANSAXLE: SHIFT LEVER: INSTALLATION; 2013 MY FR-S [03/2012 -]
1. INSTALL SHIFT LEVER ASSEMBLY
(a) Install and tighten the 4 bolts in the sequence shown in the illustration.
Torque : 18 Nm (184 kgf-cm, 13 ft-lbf)
(b) Engage the wire harness clamp.
(c) Connect the 2 connectors.
2. INSTALL CONSOLE BOX ASSEMBLY
Installation
3. CONNECT FLOOR SHIFT GEAR SHIFTING ROD SUB-ASSEMBLY
(a) While pushing the shift lock release button, move the shift lever to N.
(b) Using tape, hold a 0.3 mm feeler gauge on the floor shift control select lever.
(c) Using tape, attach the floor shift control select lever to the console box assembly.
NOTICE:
Make sure that the feeler gauge is not on the area shown in the illustration.
(d) Turn the transmission control shaft lever RH of the park/neutral position switch assembly counterclockwise until it stops, and turn it clockwise 2 notches to set it to the N position.
(e) Temporarily install the floor shift gear shifting rod sub-assembly with the nut.
(f) Tighten the nut while lightly pushing the lever rearward.
Torque : 18 Nm (184 kgf-cm, 13 ft-lbf)
NOTICE:
Do not push the lever too hard.
4. INSPECT SHIFT LEVER POSITION Initial Inspection and Diagnostic Overview
5. INSTALL NO. 2 ENGINE UNDER COVER Installation
6. INSTALL NO. 1 ENGINE UNDER COVER Installation