FREE REPAIR MANUALS & LABOR GUIDES 1982-2013 Vehicles
Courtesy of Operation CHARM: Car repair manuals for everyone.

Installation





2AR-FE BATTERY / CHARGING: GENERATOR: INSTALLATION

1. INSTALL GENERATOR ASSEMBLY

(a) Install the generator with the 2 bolts.

Torque : 52 Nm (530 kgf-cm, 38 ft-lbf)

(b) Install the wire harness clamp bracket with the bolt.

Torque : 8.4 Nm (85 kgf-cm, 74 in-lbf)

(c) Connect the generator wire with the nut.

Torque : 9.8 Nm (100 kgf-cm, 87 in-lbf)

(d) Install the terminal cap.

(e) Connect the generator connector.

2. INSTALL WIRE HARNESS CLAMP BRACKET

(a) Install the clamp bracket with the bolt.

Torque : 10 Nm (102 kgf-cm, 7 ft-lbf)

(b) Attach the wire harness clamp to the clamp bracket.

3. INSTALL FAN AND GENERATOR V BELT

Installation

4. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

NOTICE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected Repair Instruction - Initialization.