Installation
U241E AUTOMATIC TRANSAXLE: PARK / NEUTRAL POSITION SWITCH: INSTALLATION
INSTALLATION
1. INSTALL PARK/NEUTRAL POSITION SWITCH ASSEMBLY
(a) Install the switch to the manual valve shaft.
(b) Temporarily install the 2 bolts.
(c) Place a new lock plate and tighten the nut.
Torque: 6.9 Nm (70 kgf-cm, 61 in-lbf)
(d) Temporarily install the control shaft lever.
(e) Turn the lever counterclockwise until it stops, then turn it clockwise 2 notches.
(f) Remove the control shaft lever.
(g) Align the groove with the neutral basic line.
(h) Hold the switch in position and tighten the 2 bolts.
Torque: 5.4 Nm (55 kgf-cm, 48 in-lbf)
(i) Using a screwdriver, stake the nut with the lock plate.
(j) Install the control shaft lever, with the washer and nut.
Torque: 13 Nm (132 kgf-cm, 10 ft-lbf)
(k) Connect the switch connector.
2. INSTALL TRANSMISSION CONTROL CABLE ASSEMBLY
(a) Install the control cable and clip to the control cable bracket with the clip.
(b) Temporarily install the control cable to the control shaft lever with the nut.
3. INSTALL ENGINE UNDER COVER LH
4. ADJUST SHIFT LEVER POSITION
(a) Adjust the shift lever position Adjustments.
5. INSPECT SHIFT LEVER POSITION
(a) Inspect the shift lever position Adjustments.
6. INSPECT PARK/NEUTRAL POSITION SWITCH ASSEMBLY
(a) Inspect the park/neutral position Testing and Inspection.
7. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
8. PERFORM INITIALIZATION
(a) Perform initialization Testing and Inspection.
NOTE: Certain systems need to be initialized after disconnecting and reconnecting the cable from the negative (-) battery terminal.