Test E: The Demand Lamps Are Inoperative
PINPOINT TEST E: THE DEMAND LAMPS ARE INOPERATIVENormal Operation
The smart junction box (SJB) supplies voltage to the demand lamps on circuit CLN09 (YE/GN). The demand lamps are grounded through circuit GD139 (BK/YE). The glove compartment lamp (MKZ only) is case grounded.
This pinpoint test is intended to diagnose the following:
- Wiring, terminals or connectors
- SJB