Canister Purge Solenoid: Testing and Inspection
2AZ-FXE EMISSION CONTROL: PURGE VALVE: INSPECTION
1. INSPECT NO. 1 VACUUM SWITCHING VALVE ASSEMBLY
(a) Measure the resistance according to the value(s) in the table below.
Standard Resistance:
If the result is not as specified, replace the No. 1 vacuum switching valve assembly.
(b) Check operation of the No. 1 vacuum switching valve assembly.
(1) Blow air into port E. Check that air does not come out of port F.
Text in Illustration
(2) Apply battery voltage across the terminals.
(3) Blow air into port E. Check that air comes out from port F.
If the result is not as specified, replace the No. 1 vacuum switching valve assembly.