Installation
P410 HYBRID TRANSMISSION / TRANSAXLE: SHIFT LEVER: INSTALLATION
1. INSTALL TRANSMISSION INSTRUMENT PANEL SHIFT ASSEMBLY
(a) Connect the 2 connectors to transmission instrument panel shift assembly.
(b) Install the transmission instrument panel shift assembly with the 3 nuts.
Torque : 12 Nm (122 kgf-cm, 9 ft-lbf)
2. INSTALL CONSOLE BOX LH Installation
3. INSTALL CONSOLE BOX INSERT Installation
4. INSTALL REAR CONSOLE BOX ASSEMBLY Installation
5. INSTALL CONSOLE BOX CARPET Installation
6. INSTALL REAR CONSOLE BOX POCKET Installation
7. INSTALL INTEGRATION CONTROL AND PANEL ASSEMBLY Installation
8. INSTALL UPPER CONSOLE PANEL SUB-ASSEMBLY Installation
9. INSTALL UPPER NO. 1 CONSOLE PANEL GARNISH Installation
10. INSTALL UPPER NO. 2 CONSOLE PANEL GARNISH Installation
11. INSTALL LOWER CENTER INSTRUMENT PANEL FINISH PANEL Installation
12. INSTALL SHIFT LEVER KNOB SUB-ASSEMBLY Installation
13. CONNECT CABLE TO NEGATIVE AUXILIARY BATTERY TERMINAL
NOTICE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected Repair Instruction - Initialization.
14. INSTALL REAR FLOOR BOARD UPPER NO. 3 PLATE Installation
15. INSTALL DECK FLOOR BOX RH Installation
16. INSTALL REAR NO. 3 FLOOR BOARD Installation
17. INSTALL REAR DECK FLOOR BOX Installation
18. INSTALL REAR NO. 2 FLOOR BOARD Installation
19. INSPECT SHIFT LEVER
(a) Turn the power switch on (READY).
(b) Check that all available shift positions can be selected by moving the shift lever.
HINT
After the transmission instrument panel shift assembly is replaced with a new one, perform the above operation. If this operation is not performed, moving the shift lever may not initially select shift positions.