Installation
1UR-FSE EMISSION CONTROL: PURGE VALVE: INSTALLATION
INSTALLATION
1. INSTALL PURGE VSV
(a) Install the purge VSV with the bolt.
Torque: 21 Nm (214 kgf-cm, 15 ft-lbf)
(b) Connect the 2 purge line hoses to the purge VSV.
(c) Connect the purge VSV connector.
2. CONNECT ENGINE WIRE Installation
3. INSTALL AIR CLEANER CAP LH
(a) Install the air cleaner cap LH.
4. INSTALL AIR CLEANER CAP RH
(a) Install the air cleaner cap RH.
5. INSTALL INTAKE AIR CONNECTOR PIPE Installation
6. INSTALL NO. 1 AIR CLEANER INLET Installation
7. INSTALL V-BANK COVER SUB-ASSEMBLY Installation
8. INSTALL ENGINE ROOM SIDE COVER LH Installation
9. INSTALL ENGINE ROOM SIDE COVER RH Installation
10. INSTALL AIR CLEANER INLET COVER Installation
11. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
NOTE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected Repair Instruction - Initialization.
12. INSTALL COWL TOP VENTILATOR LOUVER RH Installation