Vacuum Reservoir: Testing and Inspection
INSPECTION PROCEDURE
1. Remove the vacuum chamber.
2. Visually inspect the outer surface for damage.
3. Blow air from port A and verify that there is no air-flow.
4. Blow air from port B and verify that there is air-flow.
5. If not as specified, replace the vacuum chamber or one-way check valve.