Part Numbers and Campaign Operation Codes
Claims for this campaign will be reimbursed under the following Campaign Codes:1. 910011I0 1.1 hours
^ Replacement of primary main air jet
^ Installation of carburetor choke shim
^ Cleaning of sub-EGR valve
^ Ignition timing resetting
^ Inspection of exhaust manifold
^ Inspection of jet mixture solenoid
2. 910011RA 1.1 hours
^ Replacement of primary main air jet
^ Installation of carburetor choke shim
^ Cleaning of sub-EGR valve
^ Ignition timing resetting
^ Inspection of exhaust manifold
^ Inspection of jet mixture solenoid
^ Replacement of air pipe
3. 910011RB 1.2 hours
^ Replacement of primary main air jet
^ Installation of carburetor choke shim
^ Cleaning of sub-EGR valve
^ Ignition timing resetting
^ Inspection of exhaust manifold
^ Replacement of jet mixture solenoid
4. 910011RC 1.2 hours
^ Replacement of primary main air jet
^ Installation of carburetor choke shim
^ Cleaning of sub-EGR valve
^ Ignition timing resetting
^ Inspection of exhaust manifold
^ Replacement of jet mixture solenoid
^ Replacement of air pipe
5. 910011RD 1.5 hours
^ Replacement of primary main air jet
^ Installation of carburetor choke shim
^ Cleaning of sub-EGR valve
^ Ignition timing resetting
^ Replacement of exhaust manifold
^ Inspection of jet mixture solenoid
6. 910011RE 1.5 hours
^ Replacement of primary main air jet
^ Installation of carburetor choke shim
^ Cleaning of sub-EGR valve
^ Ignition timing resetting
^ Replacement of exhaust manifold
^ Inspection of jet mixture solenoid
^ Replacement of air pipe
7. 910011RF 1.5 hours
^ Replacement of primary main air jet
^ Installation of carburetor choke shim
^ Cleaning of sub-EGR valve
^ Ignition timing resetting
^ Replacement of exhaust manifold
^ Inspection of jet mixture solenoid
^ Replacement of oxygen sensor
8. 910011RG 1.6 hours
^ Replacement of primary main air jet
^ Installation of carburetor choke shim
^ Cleaning of sub-EGR valve
^ Ignition timing resetting
^ Replacement of exhaust manifold
^ Inspection of jet mixture solenoid
^ Replacement of catalyst case
9. 910011RH 1.5 hours
^ Replacement of primary main air jet
^ Installation of carburetor choke shim
^ Cleaning of sub-EGR valve
^ Ignition timing resetting
^ Replacement of exhaust manifold
^ Inspection of jet mixture solenoid
^ Replacement of air pipe
^ Replacement of oxygen sensor
10. 910011RJ 1.6 hours
^ Replacement of primary main air jet
^ Installation of carburetor choke shim
^ Cleaning of sub-EGR valve
^ Ignition timing resetting
^ Replacement of exhaust manifold
^ Inspection of jet mixture solenoid
^ Replacement of air pipe
^ Replacement of catalyst case
11. 910011RK 1.6 hours
^ Replacement of primary main air jet
^ Installation of carburetor choke shim
^ Cleaning of sub-EGR valve
^ Ignition timing resetting
^ Replacement of exhaust manifold
^ Inspection of jet mixture solenoid
^ Replacement of oxygen sensor
^ Replacement of catalyst case
12. 910011RL 1.6 hours
^ Replacement of primary main air jet
^ Installation of carburetor choke shim
^ Cleaning of sub-EGR valve
^ Ignition timing resetting
^ Replacement of exhaust manifold
^ Inspection of jet mixture solenoid
^ Replacement of air pipe
^ Replacement of oxygen sensor
^ Replacement of catalyst case
13. 910011RM 1.6 hours
^ Replacement of primary main air jet
^ Installation of carburetor choke shim
^ Cleaning of sub-EGR valve
^ Ignition timing resetting
^ Replacement of exhaust manifold
^ Replacement of jet mixture solenoid
14. 910011RN 1.6 hours
^ Replacement of primary main air jet
^ Installation of carburetor choke shim
^ Cleaning of sub-EGR valve
^ Ignition timing resetting
^ Replacement of exhaust manifold
^ Replacement of jet mixture solenoid
^ Replacement of air pipe
15. 910011RP 1.6 hours
^ Replacement of primary main air jet
^ Installation of carburetor choke shim
^ Cleaning of sub-EGR valve
^ Ignition timing resetting
^ Replacement of exhaust manifold
^ Replacement of jet mixture solenoid
^ Replacement of oxygen sensor
16. 910011RQ 1.7 hours
^ Replacement of primary main air jet
^ Installation of carburetor choke shim
^ Cleaning of sub-EGR valve
^ Ignition timing resetting
^ Replacement of exhaust manifold
^ Replacement of jet mixture solenoid
^ Replacement of air pipe
17. 910011RR 1.6 hours
^ Replacement of primary main air jet
^ Installation of carburetor choke shim
^ Cleaning of sub-EGR valve
^ Ignition timing resetting
^ Replacement of exhaust manifold
^ Replacement of jet mixture solenoid
^ Replacement of air pipe
^ Replacement of oxygen sensor
18. 910011RS 1.7 hours
^ Replacement of primary main air jet
^ Installation of carburetor choke shim
^ Cleaning of sub-EGR valve
^ Ignition timing resetting
^ Replacement of exhaust manifold
^ Replacement of jet mixture solenoid
^ Replacement of air pipe
^ Replacement of catalyst case
19. 910011RT 1.7 hours
^ Replacement of primary main air jet
^ Installation of carburetor choke shim
^ Cleaning of sub-EGR valve
^ Ignition timing resetting
^ Replacement of exhaust manifold
^ Replacement of jet mixture solenoid
^ Replacement of oxygen sensor
^ Replacement of catalyst case
20. 910011RU 1.7 hours
^ Replacement of primary main air jet
^ Installation of carburetor choke shim
^ Cleaning of sub-EGR valve
^ Ignition timing resetting
^ Replacement of exhaust manifold
^ Replacement of jet mixture solenoid
^ Replacement of air pipe
^ Replacement of oxygen sensor
^ Replacement of catalyst case