P0765
Test 1 Through 2:
Test 3 Through 7:
Test 8 Through 11:
SYMPTOM:
P0765-UD SOLENOID CIRCUIT
When Monitored and Set Condition:
P0765-UD SOLENOID CIRCUIT
When Monitored:
Initially at power-up, then every 10 seconds thereafter. They will also be tested immediately after a gear ratio or pressure switch error is detected.
Set Condition:
Three consecutive solenoid continuity test failures, or one failure if test is run in response to a gear ratio or pressure switch error.
POSSIBLE CAUSES
RELATED RELAY DTC'S PRESENT
INTERMITTENT WIRING & CONNECTORS CONDITIONS
UD SOLENOID CONTROL CIRCUIT OPEN
UD SOLENOID CONTROL CIRCUIT SHORT TO GROUND
TRANSMISSION RELAY OUTPUT CIRCUIT OPEN
UD SOLENOID CONTROL CIRCUIT SHORT TO VOLTAGE
UD SOLENOID INOPERATIVE
REPLACE THE TCM